Liquid Screed
Contact Us
  • Screed Slide 1
  • Screed Slide 2
  • Screed Slide 3
  • Screed Slide 4
  • Screed Slide 5
  • Screed Slide 6
  • Screed Slide 7
  • Screed Slide 8
  • Screed Slide 9
  • Screed Slide 10

Aftercare Guide

Foot Traffic

Liquid screed can usually accept light site traffic after about 24 – 48 hours. It is sometimes possible to traffic the morning after the previous installation.

Full site traffic should be avoided for at least 2-3 days. Where heavier site traffic is expected, it is advisable to temporarily protect these areas with plywood sheets, which should be removed in good time to permit adequate drying.

Cufing

It is essential that the material is allowed to cure undisturbed for the first 24-48 hour period. The floor area should be closed to all traffic.

Traditional curing procedures using impermeable membranes are not necessary but rapid loss of moisture should be avoided during the first 24-48 hours.

Where windows and/or doors are not installed, a temporary provision must be made using appropriate materials.

Direct sunlight must be avoided during the first 24-48 hour curing period. Windows and glass doors with a southern aspect should be covered temporarily for this period.

After the first 24-48 hours of curing doors and windows may be opened.

Drying

It is important to note that drying times relate to ambient humidity, temperature and number of air changes. In general, liquid screed installed as an un-bonded system dries at a rate of 1mm per day for the first 4omm of depth and 0.5mm per day for any depth over and above this. This is provided a temperature of 20 degrees celcius is maintained and 65% relative humidity.

Where drying temperatures are high and humidity is low, drying time will be less. Unlike conventional cement / sand screeds, dehumidifiers may be used to accelerate drying. These should only be used 2 to 5 days after placing.

Where under floor heating is installed this can be used to decrease drying times but should only be used after the first 7 days. The heating system temperature should be built up gradually at a rate of 5 degrees celsius per day.

Prior to the installation of a floor covering, liquid screed must have dried to an approved level. For moisture sensitive coverings the code of practice value is stated as 75% relative humidity, which equates to 0.5% moisture content by mass. Below this value impermeable floor finishes may be applied.

Drying Out Period – After 24/48 Hours

Avoid water ingress to completed screeds and arrange to dry out accidental ingress as soon as possible. The screed may suffer a minor loss of strength if it becomes wet however, this strength will generally be regained when it dries out.

Open windows on all sides of the building in order to achieve good cross ventilation and air changes thus accelerating the drying out process. A typical 4omm thick screed can be expected to dry to 0.5% moisture content in 40 days under ideal conditions.

This can however be greatly affected by actual conditions.

 

UK Coverage

Offering a professional Liquid screed, Underfloor heating, Preparation and Aftercare service throughout Devon.

Underfloor Heating
Liquid Drip Orange Drip
Liquid Screed and Underfloor Heating One Smooth Solution!
Get Quote